The first step is to apply for a building permit with the city/county.
It will be approximately three weeks before the permit is issued.
| Week 1: | |
|
|
|
| Received Permit from City | Lot BEFORE cleared |
|
|
|
| Lot Cleared | Framed Foundation |
Week 2: |
|
|
|
|
| Plumbed area | Poured Foundation |
Week 3: |
|
|
|
|
| Framing Home | |
Week 4: |
|
|
|
|
| Finished Framing | Trusses in Place |
|
|
|
|
Plywood Exterior Started |
Started Roof Decking |
|
Week 6: |
|
|
|
|
| Decorative Front Trusses | Wrap Siding & Roof Decking |
|
|
|
|
Complete Roof Decking |
|
|
Week 7: |
|
|
|
|
| Shingled Roof, Start ducts |
Front/Rear Doors, transom |
Week 8: |
|
|
|
|
| Hardee Board, Electrical |
|
|
Week 9: |
|
|
|
|
| Tankless HtWtr, Air Handler |
|
Week 10: |
|
|
|
|
| Shower pan, Tub, Electrical | Fireplace, A/C Completed |
|
|
|
|
Week 11: |
|
|
|
|
| Start exterior paint | Insulation Installed |
| Week 12: |
|
|
|
|
| Sheetrock, Ceiling painted | |
|
Week 13: |
|
|
|
|
| Exterior painted | Poured Driveway & Walkway |
|
|
|
|
|
|
|
|